6957 Policy – Construction Change Orders

In order to expedite change orders on construction contracts in the Bellingham School District, the Board has determined that for change orders where the amount involved is 5% or less of the total project cost, but not in excess of $250,000, such change orders may be approved by the Superintendent or his/her designee. Payment may then be made through the business office.

Adopted: 09/27/07
Revised: 03/22/12