6957 Policy – Construction Change Orders

In order to expedite change orders on construction contracts in Bellingham Public Schools, change orders where the amount is 10% or less of the total project cost, but not in excess of $250,000, may be approved by the superintendent or their designee. Payment may then be made through the business office

Approved By: Greg Baker, Superintendent and Kelly Bashaw, School Board President
Adopted/Previous Revisions: 09/27/07; 03/22/12
Adopted/Revised: 09/27/07; 03/22/12; 03/13/19;
Updated: 04/20/22
Superintendent or Board Approved: Board Approved